Hillje-Blu Lacy 765-kV Transmission Line: Map, Status, & Landowner Information
Routes Are Still Preliminary. Your Window to Act Is Now.
AEP Texas and CenterPoint Energy have notified the preliminary routes for the Hillje to Blu Lacy 765-kV line, but nothing is final yet. Here's what you need to know and what you can do today.
Hillje to Blu Lacy at a Glance
CenterPoint Energy and AEP Texas state that this is a joint effort to build roughly 155 miles of new 765 kV transmission line between Wharton and Nueces counties, plus two new substations. The Hillje to Blu Lacy line is one segment of the larger TX 765 kV STEP Eastern Backbone. The Eastern Backbone is one part of ERCOT's broader Strategic Transmission Expansion Plan (STEP), which also includes the Permian Basin Reliability Plan, totaling roughly $33 billion before financing and maintenance costs. This marks the first time 765 kV transmission lines have ever been built in Texas.
Current Status
CenterPoint Energy and AEP Texas are in the preliminary planning and route input phase for this project. They've been holding open houses to collect landowner feedback, but no route has been finalized and no formal application has been filed with the Public Utility Commission of Texas. This is the window landowners have to organize and weigh in before the project moves into a formal docket. The timeline presented (below) indicated that the transmission service providers plan to file a formal CCN application early 2027.
Deadlines & Meetings
August 26, 2026 - Landowner feedback is being accepted through August 26, submitted to Hillje-BluLacyResiliencyProject@CenterPointEnergy.com; if you have questions about what information to share, consider consulting an attorney before you submit.
You can find the feedback form here (link).
CenterPoint and AEP Texas have also held open houses across the project area:
- July 27, 2026: Robstown, TX
- July 28, 2026: Refugio, TX
- July 29, 2026: El Campo, TX
- July 30, 2026: Inez, TX
- August 1, 2026: Victoria, TX
- August 18, 2026: Edna, TX — details here
A recording of the virtual webinar is also available here (CenterPoint Energy) or here (AEP) for those who couldn't attend in person.
Counties Affected
CenterPoint Energy and AEP Texas have notified the following counties as part of this preliminary phase:
- Aransas County
- Bee County
- Goliad County
- Jackson County
- Jim Wells County
- Lavaca County
- Live Oak County
- Matagorda County
- Nueces County
- Refugio County
- San Patricio County
- Victoria County
- Wharton County
Taking Action During the Preliminary Phase
During the preliminary phase, landowners have several options for learning more, asking questions, documenting concerns, and making their voices heard. You do not have to wait for a notice letter to begin preparing. Texas transmission cases can move quickly once an application is filed. There are practical steps you can take now. The information below is intended to help you understand some of the actions you may choose to take and provide the resources you need to take them.
This is not legal advice, and there is no single “right” way to participate. Every property and situation is different. These are simply options available to landowners who want to become informed and engaged before a formal application is filed.